This post-war home had good bones but needed everything modernised. We stripped the interior back to the frame and rebuilt it — new kitchen, bathrooms, flooring, windows and a reconfigured floor plan that suits the way the family lives today. The result feels like a new home, retained in a street the clients love.

The Challenge

A full transformation of a post-war home means rewiring, replumbing and re-roofing — and this one also carried dated wiring, aged pipework and termite damage in two wall frames that only revealed themselves once the linings came off. Matching new windows to the original brick profile was its own puzzle.

Our Solution

We planned the rewiring and replumbing as a single coordinated stage with the strip-out, which saved the client the cost of separate attendances. The termite damage was treated, the affected frames rebuilt to spec, and the window manufacturer cut custom sills to match the existing brick course so the new windows sit in the wall like they always belonged there.

The Outcome

The clients gained a home that performs like new construction — new services, new thermal envelope, new finishes — while keeping the street presence and character they bought into. Delivered in four months, and at a fraction of the cost of a knockdown-rebuild, the project is our most-requested reference when new clients are weighing renovation against rebuilding.

WHAT THIS PROJECT TAUGHT US

The biggest lesson from a whole-home transformation is sequencing. Stripping the house back meant we could rewire, replumb and treat the termite damage as one coordinated stage — saving the client separate trade attendances and weeks of waiting. Combined with custom window detailing matched to the original brickwork, the project shows why renovation is a builder's job and not a weekend one: the hidden work is where the value is created, and the visible work is where it is judged.

SCOPE OF WORKS
  • Strip-out and reconfiguration of the floor plan
  • Two new bathrooms and laundry
  • New kitchen with upgraded appliances
  • New windows, doors and external repaint
  • Electrical rewiring and lighting plan